Management Science Vol. 57 No. 4 2011

Integrated Sequencing and Scheduling in Coil Coating

Wiebke Höhn1; Felix G. König1; Rolf H. Möhring1; Marco E. Lübbecke2

1 Institut für Mathematik, Technische Universität Berlin, 10623 Berlin, Germany · 2 Department of Operations Research, RWTH Aachen University, 52056 Aachen, Germany

Abstract

We consider a complex planning problem in integrated steel production. A sequence of coils of sheet metal needs to be color coated in consecutive stages. Different coil geometries and changes of colors necessitate time-consuming setup work. In most coating stages one can choose between two parallel color tanks. This can either reduce the number of setups needed or enable setups concurrent with production. A production plan comprises the sequencing of coils and the scheduling of color tanks and setup work. The aim is to minimize the makespan for a given set of coils. We present an optimization model for this integrated sequencing and scheduling problem. A core component is a graph theoretical model for concurrent setup scheduling. It is instrumental for building a fast heuristic that is embedded into a genetic algorithm to solve the sequencing problem. The quality of our solutions is evaluated via an integer program based on a combinatorial relaxation, showing that our solutions are within 10% of the optimum. Our algorithm is implemented at Salzgitter Flachstahl GmbH, a major German steel producer. This has led to an average reduction in makespan by over 13% and has greatly exceeded expectations.

DOI
10.1287/mnsc.1100.1302
Volume
57
Issue
4
Pages
647-666
Language
en
Sources
bibtex:phds-export.bib openalex crossref

Cite