Management Science Vol. 4 No. 3 1958

A Computational Approach to the Economic Lot Scheduling Problem

Jack Rogers

Assistant Professor of Business Administration, University of California, at Berkeley

Abstract

In practice, the economic lot quantity problem and the scheduling problem often are treated separately in production planning. However, when a number of items must be supplied continuously and the same means of production must be employed for several of the items non-concurrently, the “economic lot scheduling problem” may have to be dealt with. Addressing itself to a reduced version of this problem, the article outlines a computational approach to finding a feasible and minimum cost (set-up plus storage) production schedule for a group of items which must be available continuously though produced consecutively in a single production center.

DOI
10.1287/mnsc.4.3.264
Volume
4
Issue
3
Pages
264-291
Language
en
Sources
bibtex:phds-export.bib openalex crossref