Note—Optimal Component Acquisition for a Single-Product, Single-Demand Assemble-to-Order Problem with Expediting

Ke Fu1; Vernon Ning Hsu2,3,4; Chung-Yee Lee5

1 Sun Yat‐Sen University · 2 George Mason University · 3 Australian Institute of Business · 4 UNSW Sydney · 5 Hong Kong University of Science and Technology

Abstract

We consider a component acquisition problem for a contract manufacturer who faces a one-time stochastic demand for a single product consisting of a number of components. Components can be ordered early at normal prices before the demand is revealed, or they can be replenished later at higher prices due to expediting. In addition, the customer pays a price for the final product that is nonincreasing in the delivery lead time to discourage late delivery. We propose a cost-minimization model and develop an efficient polynomial time algorithm to solve the problem.

DOI
10.1287/msom.1070.0202