MODELING TIME‐COST TRADE‐OFFS IN CPM NETWORKS

Chris Pilot1; Stephen Pilot2

1 Maine Maritime Academy · 2 AT&T, Rolling Meadows, Illinois 60008, USA

Abstract

A new type of PERT/CPM methodology is introduced whereby the individual activities within a project management network are endowed with resistive and capacitive elements. This methodology will enable us to mathematically define a completion time for the various activities and to relate the completion time to relevant cost in the completion of a particular task. It will also allow us to define the work done, and the rate at which work is being done, in an activity as a function of the applied effort and resource outlay. As a consequence, both the resource expenditure and the work done can be tracked within a network as a function of time.